1. Clean the profile ring, the inside of the socket and the groove for the ring.
-
2. Wet the profile ring with clean water. Squeeze it into a heart shape, the let it shape into the groove, and check alignment.
-
3. The pipe end provided with a 15 factory made chamfer, must be cleaned and coated with lubricant before pushing into the socket. Mark insertion depth if not already provided.
-
4. Push together only up to the insertion mark to take care of expansion. For large diameter pipes, a pipe jack may be used.
-
5. If shorter lengths are required, cut off the pipe ends squarely using fine-toothed saw and a miter box.
-
6. Prior to insertion in the socket the cut-off pipe must be deburred and chamfered approx 15, using a file or chamfering tool.